Cronulla STP – Mechanical Works Project –

Improve Reliability of Cronulla STP – 

Cronulla Sewage Treatment Plant (STP) was upgraded from a primary to a tertiary STP in 2001. Detailed audits identified many mechanical, electrical and civil assets were now past their design life and showing signs of fatigue, corrosion and poor reliability.

The aim of this project was to improve reliability and robustness and to renew and refurbish deteriorated mechanical assets in the old plant.

Design, Construct, Refurbish

PET scope of works included:

♦  Replace valves, handrails, pipework, actuators, instrumentation etc
♦  Replace washpactors
 Replace grit classifier system
♦  Design and install new hypo system
 Replace interstage pumps
 Gas flare upgrade and alteration
♦  Replace penstocks on sedimentation tanks
♦  Replace compressor and associated equipment
♦  Install sump pumps

 


To Top

Focus

♦ Electrical & Mechanical Design

♦ Construction

 Process Proving

Client

♦ Sydney Water Corporation

Contractor

♦ Process Engineering Technologies Pty Ltd

Project Value

♦ $2.2m

 

 