Kincumber & Woy Woy STPs – Inlet Works Upgrade –

Design & Construction of Facilities – 

PET upgraded the Inlet Works of  Kincumber & Woy Woy Sewage Treatment Plants (STP).  

PET scope of works included:

 Repair and protective coatings to Inlet channels and Grit tanks at Kincumber STP
 Design/ supply and installation of penstocks and stopboards at Kincumber
  Design/ supply and installation of new Step screens
 Design/ supply and installation of screenings and grit washings and disposal systems
  Associated civil and electrical works
  Removal of existing redundant plant
 Commissioning of new equipment


To Top

Focus

♦ Electrical, Civil & Mechanical Design

♦ Construction

♦ Process Proving

Client

♦ Gosford City Council

Contractor

♦ Process Engineering Technologies Pty Ltd

Project Value

♦ $4m

 

 